Tordera SWRO storage tanks built within 16 weeks

John Lyndon-Taylor, CST Vulcan

One of the 10,000 m³ tanks under construction at Tordera.

One of the 10,000 m³ tanks under construction at Tordera.

The challenge of upgrading and nearly doubling the potable water storage capacity as part of an upgrade of the Tordera seawater reverse-osmosis desalination plant in Blanes (Girona) near Barcelona, Spain, within a rigorous timeframe, was awarded to CST Vulcan, a division of CST Industries Inc.

Using a specialised jacking system, allowing the tanks to be built from the ground up, construction was completed in August 2009, in less than 16 weeks total, allowing the overall project to continue on time and as planned.