Case study: Larnaca SWRO Plant Renovation – design, installation and commissioning

Learn how Flowserve worked closely with the Cyprus Water Department and M.N Larnaca to provide low-cost drinking water for 16 million people

Case study: Larnaca SWRO Plant Renovation – design, installation and commissioning

In 2011 it was decided to build a new desalination plant within the existing building layout with new highly efficient equipment, rather than retrofitting the existing installation, and a new tender was issued. By contracting with one supplier for both the DWEER™ energy recovery devices and all the main pump services, the engineering procurement and construction company was able to gain significant efficiencies not previously experienced.

This paper outlines the development, installation and commissioning of the new SWRO plant at Larnaca, and the benefits of having a one-supplier contract.

Case study contents:

  • Introduction
  • New Larnaca design in 2013
  • New high-pressure membrane feed RO train design
  • Improved high-pressure pumps
  • Improved energy recovery system
  • Optimised energy recovery system
  • Installation
  • Commissioning